Construction, Carpentry & Concrete Masonry, Block & Reinforcement ACI 318-19 cover, spacing and splice provisions

Rebar Spacing & Quantity Calculator

Give this calculator a slab or footing plan, a bar spacing and a cover dimension and it lays out the grid: how many bars run each way, how long each one is, how many 20-foot sticks that comes to once lap splices are counted, how many tie intersections your crew has to wire, and the steel area per foot the grid actually delivers. The last number is the one that matters to an inspector — #4 bars at 12 in on centre give 0.20 in² per foot, and whether that is enough depends on the slab thickness and on what the engineer specified, not on habit.

Calculator

This calculator runs in your browser. Enable JavaScript for live results — the inputs, formula and worked example below remain fully readable without it.

Inputs this calculator takes, with typical values
InputWhat to enterExample
Slab lengthThe longer plan dimension of the pour, out to out of the forms.24 ft
Slab widthThe shorter plan dimension, out to out of the forms.24 ft
Slab thicknessUsed to check the grid against the spacing and minimum-steel limits in ACI 318.5 in
Bar sizeASTM A615 imperial bar sizes; the number is the diameter in eighths of an inch.#4 — 1/2 in, 0.668 lb/ft
Spacing of bars running lengthwiseCentre-to-centre spacing measured across the width of the slab.12 in
Spacing of bars running widthwiseCentre-to-centre spacing measured along the length of the slab.12 in
Side cover to the first barClear distance from the edge of the concrete to the outermost bar; 3 in where concrete is cast against ground.3 in
Stock bar lengthThe length your supplier delivers. Twenty feet is the common stock length in North America.20 ft
Lap splice lengthA detailing rule of thumb; ACI 318 Chapter 25 requires the splice to be calculated, and it can exceed 40 diameters.40 × bar diameter

It returns

  • Stock bars to order — Whole sticks, allowing for the lap splice where a run is longer than one bar.
  • Bars running lengthwise
  • Bars running widthwise
  • Total steel in the slab — Placed length including the steel consumed by lap splices.
  • Total weight of steel
  • Grid intersections to tie — Every crossing. Most placers tie every intersection on the perimeter and every second one inside.
  • Steel area per foot — lengthwise bars
  • Steel area per foot — widthwise bars

The formula

n=B2cs+1
As=Abar12s

In plain text: n = floor((clear span − 2 × cover) / spacing) + 1

  • nNumber of bars in one direction (bars)
  • BSlab dimension measured across the bars (in)
  • cClear cover from the edge to the first bar (in)
  • sCentre-to-centre bar spacing (in)

The +1 counts the bar at the far edge. Forgetting it is the single most common rebar takeoff error, and on a tight grid it can cost you several bars per direction.

Updated Category Masonry, Block & Reinforcement Verified against published test cases Reading time 12 min

What a rebar layout actually consists of

A slab grid is defined by four numbers: the bar size, the spacing each way, the cover, and the plan dimensions. Everything else follows. The bar count in one direction is the clear band between the covers divided by the spacing, rounded down, plus one — the bar at the far edge. Bar length is the plan dimension less the cover at each end. Multiply and you have lineal feet; divide by stock length with an allowance for laps and you have sticks to order.

The fence-post rule is where most takeoffs go wrong. Twenty feet of clear band at 12 in spacing does not hold 20 bars, it holds 21, because you are counting posts and not gaps. On a 24 ft × 24 ft slab at 12 in on centre the difference is two bars each way — trivial. On a 200-bar highway pour it is not.

The other number worth understanding is the steel area per foot. A grid is not really "#4 at 12 inches"; structurally it is 0.20 square inches of steel in every foot of slab width. That is what an engineer specifies and what an inspector checks, and it is why #4 at 12 in and #5 at 18 in are close cousins — 0.200 against 0.207 in²/ft. Knowing the equivalence lets you substitute intelligently when a size is out of stock, subject to the engineer agreeing.

Cover, spacing limits and lap splices under ACI 318-19

Cover is the clear distance from the surface of the concrete to the nearest bar, and it exists to protect the steel from corrosion and fire. ACI 318-19 sets minimums by exposure in Table 20.5.1.3.1: 3 in where concrete is cast against and permanently in contact with ground, 1.5 in for #5 and smaller exposed to earth or weather, and less for interior members not exposed. On a slab on grade poured over a vapour barrier the sides are typically formed, so 1.5 in side cover is common; a footing poured against a trench wall gets 3 in.

Maximum spacing has two different limits and they get confused constantly. For shrinkage and temperature reinforcement, ACI 318-19 caps spacing at the lesser of five times the slab thickness and 18 in, with a minimum reinforcement ratio of 0.0018 of the gross concrete area for Grade 60 deformed bars. For flexural reinforcement in one-way slabs the cap is tighter — the lesser of three times the thickness and 18 in. This calculator checks your spacing against both and tells you which one you have crossed.

Lap splices transfer force from one bar to the next by bond with the surrounding concrete. ACI 318 Chapter 25 requires the splice length to be calculated from the development length, and it depends on bar size, concrete strength, cover, confinement, epoxy coating and whether the bar is a top bar. The 40-diameter figure this calculator defaults to is a detailing rule of thumb that is often conservative for #4 and #5 bars in ordinary conditions and is not a substitute for the calculation. Use whatever the drawings specify.

Worked example: a 24 ft × 24 ft slab with #4 at 12 in each way

A 24 ft square, 5 in thick slab on grade, formed edges with 3 in cover, #4 bars at 12 in on centre both ways, 20 ft stock, 40-diameter laps.

  1. Clear band. 24 ft × 12 = 288 in, less 2 × 3 in cover = 282 in in each direction.
  2. Bar count. floor(282 ÷ 12) + 1 = 23 + 1 = 24 bars each way, 48 bars in total.
  3. Bar length. 24 ft − 2 × 3 in = 24 − 0.5 = 23.5 ft per bar.
  4. Splices. 23.5 ft exceeds the 20 ft stock, so each run needs a second stick. Lap = 40 × 0.5 in ÷ 12 = 1.667 ft. Reach of the second stick = 20 − 1.667 = 18.333 ft, and 23.5 − 20 = 3.5 ft remains, so one extra stick does it: 2 sticks per run.
  5. Order. 48 runs × 2 = 96 stock bars of 20 ft.
  6. Placed steel. 48 × 23.5 = 1,128 ft of bar, plus 48 splices × 1.667 ft = 80 ft of lap, giving 1,208 ft.
  7. Weight. 1,208 × 0.668 lb/ft = 807 lb, about two-fifths of a ton.
  8. Ties. 24 × 24 = 576 intersections. Tying every second one inside the field and every one around the perimeter is typical practice.
  9. Steel area. 0.20 in² × 12 ÷ 12 = 0.200 in²/ft each way. Against a 5 in slab, that is 0.200 ÷ (12 × 5) = 0.0033 of the gross section, comfortably over the 0.0018 minimum.

Note how much the 20 ft stock length costs you here: 96 bars of 20 ft is 1,920 ft of steel bought to place 1,208 ft. Ordering 30 ft stock would let each 23.5 ft run come from a single stick — 48 bars, no splices, no lap waste and a much faster tie-out.

How to read the result

Look at sticks per run before anything else. If it reads 2, ask whether a longer stock length would make it 1. Splicing doubles the handling, adds lap steel you pay for and never use structurally, and creates a congested plane in the slab where every bar laps at the same station — which is precisely what detailers stagger splices to avoid. If splices are unavoidable, stagger them so no more than half the bars lap at any one section.

Then check the steel area per foot against the drawing, not against the bar callout. Substitutions are common on site and the safe way to make one is to keep the area per foot at or above what was specified. Going from #4 at 12 in (0.200 in²/ft) to #5 at 18 in (0.207 in²/ft) preserves the area but nearly doubles the spacing, which can breach the maximum-spacing rule and does change crack control. Area is necessary but not sufficient; spacing limits still apply.

Finally, treat the tie count as a labour figure, not a materials figure. Wire ties are cheap; the hours are not. A 576-intersection grid tied at every second crossing is roughly 300 ties, and a competent placer works through them quickly with a twister — but on a big pour this is exactly the number a foreman needs to schedule the crew.

Steel area per foot of slab width

Values are bar area × 12 ÷ spacing, in square inches per foot. Read across to find an equivalent substitute; read down to see what tightening the spacing buys.
Spacing#3 (0.11 in²)#4 (0.20 in²)#5 (0.31 in²)#6 (0.44 in²)#7 (0.60 in²)#8 (0.79 in²)
6 in0.2200.4000.6200.8801.2001.580
8 in0.1650.3000.4650.6600.9001.185
10 in0.1320.2400.3720.5280.7200.948
12 in0.1100.2000.3100.4400.6000.790
16 in0.0830.1500.2330.3300.4500.593
18 in0.0730.1330.2070.2930.4000.527

Bar areas are the nominal values in ASTM A615. Spacings above 18 in are outside the ACI 318-19 maximum for slab reinforcement regardless of the area they deliver.

This lays out a grid; it does not design one

Bar size and spacing come from a structural design that accounts for loads, span, subgrade support, concrete strength and serviceability. Nothing on this page determines whether a given grid is adequate. Two specific traps: reinforcement in an unreinforced slab-on-ground does not stop cracks forming, it only holds them tight, so it is no substitute for correctly spaced control joints; and steel placed on the ground instead of on chairs at the specified depth does close to nothing, because its lever arm is gone. Placement tolerance matters as much as quantity.

Mistakes that cost bars, time or an inspection

  • Forgetting the +1. Dividing the span by the spacing counts gaps, not bars. You always need one more bar than gaps.
  • Measuring cover from the form to the bar centreline. Cover is clear cover, to the outside surface of the bar — and for a grid, to the outermost bar, which is usually the one in the lower layer.
  • Ignoring lap steel in the weight. Splices add real tonnage. On the worked example above the laps are 80 ft of the 1,208 ft total, about 7%.
  • Lapping every bar at the same station. Stagger splices so no more than half the bars are spliced at any one section.
  • Substituting by bar size instead of by area per foot. Keep steel area per foot at or above the specified value, and check the maximum spacing rule separately.
  • Placing bars on the subgrade. Steel in the bottom of a slab on grade with no chairs contributes almost nothing. Use chairs, dobies or bolsters at the spacing the specification calls for.
  • Assuming 40 diameters is a legal lap. ACI 318 Chapter 25 requires the splice to be calculated. Use the drawings' figure.

Where this fits with the rest of the pour

The rebar takeoff is one line on a concrete estimate. Once the grid is set, the tonnage from this page goes straight into the rebar weight calculator for pricing and freight, and the volume of concrete around it comes from the concrete slab calculator or, for strip and spread footings, the concrete footing calculator. If the pour is small enough to mix on site, the concrete bag calculator converts the volume to bags.

For reinforced masonry rather than concrete, the layout logic is different — bars go in cells at fixed 8 in centres, so spacing is quantised — and the quantities come out of the concrete block calculator along with the grout that surrounds them. Where the footing size itself is in question, the soil bearing footing size calculator is the place to start, because a footing that is too narrow cannot be rescued with more steel.

A word on welded wire reinforcement: for a residential slab on grade, sheets of WWR are often specified instead of a bar grid, and the area-per-foot table above is the right way to compare them. Sheet reinforcement is faster to place and much easier to leave sitting on the subgrade, which is why bar on chairs remains the more reliable detail wherever the steel actually has to work.

Key terms

On centre (o.c.)
Spacing measured from the centreline of one bar to the centreline of the next, not the clear gap between them.
Clear cover
The shortest distance from the concrete surface to the outside of the nearest bar. Set by ACI 318-19 Table 20.5.1.3.1 according to exposure.
Lap splice
An overlap of two parallel bars long enough for force to transfer through the surrounding concrete. Its length is calculated, not assumed.
Chair / bolster
A support that holds reinforcement at the specified height while concrete is placed. Without it the bar ends up on the subgrade and does nothing.
As per foot
Steel cross-sectional area in each foot of slab width — bar area times twelve divided by the spacing in inches. The quantity an engineer specifies.
Shrinkage and temperature reinforcement
Steel provided to control cracking from volume change rather than to carry load. ACI 318-19 sets its minimum ratio at 0.0018 of the gross section for Grade 60 bars.

Frequently asked questions

How much rebar do I need for a 24 ft by 24 ft slab?

With #4 bars at 12 in on centre and 3 in cover, 24 bars each way at 23.5 ft long — 48 bars, 1,128 ft of placed steel, plus about 80 ft of lap if you are working from 20 ft stock. That is 96 sticks of 20 ft rebar weighing roughly 807 lb. Order 30 ft stock instead and each run comes from one stick: 48 bars, no splices and no lap waste.

What spacing should I use for a residential slab?

Take it from the engineer or the plan, not from a rule of thumb. What the code fixes is the ceiling, not the choice: ACI 318-19 caps shrinkage and temperature steel at the lesser of five slab thicknesses and 18 in, and requires at least 0.0018 of the gross section for Grade 60 bars. #4 at 12 in in a 5 in slab gives 0.0033, well above the minimum, which is why it is such a common detail — but a slab carrying a point load or spanning soft ground needs a design.

How long should a rebar lap splice be?

Whatever ACI 318 Chapter 25 gives for your conditions — the length depends on bar size, concrete strength, cover, confinement, coating and bar position, and it is a calculation, not a constant. The 40-diameter default here is a common detailing rule of thumb (20 in for a #4, 25 in for a #5) and it is what many residential drawings show, but if your drawings specify a different figure, use theirs.

Do I count the bar at the very edge?

Yes, and that is exactly what the "+1" in the formula is for. If your clear band is 282 in and your spacing is 12 in, there are 23 full gaps and 24 bars. Counting gaps instead of bars is the most common rebar takeoff error. The first and last bars sit one cover dimension in from each edge of the concrete.

Can I substitute #5 bars at 18 in for #4 bars at 12 in?

They deliver almost identical steel area — 0.207 versus 0.200 in² per foot — so on area alone the swap works. But spacing limits apply independently: 18 in is at the ACI 318-19 ceiling and above the tighter three-times-thickness limit for flexural steel in a one-way slab under 6 in thick. Wider spacing also gives coarser crack control. Get the engineer's agreement before substituting.

How many ties do I need, and do I have to tie every intersection?

The calculator reports every intersection in the grid; common practice is to tie every intersection around the perimeter and every second one in the field, which is roughly half the total. The purpose is to keep the mat from shifting during the pour, not to transfer force — ties carry no structural load. Follow the specification if one is given, because some agencies do require every intersection tied.

Does this work for a footing as well as a slab?

Yes for a spread footing or a mat, where the reinforcement really is a two-way grid — enter the pad dimensions and 3 in cover for concrete cast against ground. A continuous strip footing is different: it usually carries two to four longitudinal bars with transverse ties or none at all, so set one spacing to give the bar count you want and read the lineal feet, or work the run straight from the length.

What does the steel weigh per foot?

The nominal ASTM A615 unit weights are 0.376 lb/ft for #3, 0.668 for #4, 1.043 for #5, 1.502 for #6, 2.044 for #7 and 2.670 for #8. They come from 2.67 times the square of the bar diameter in inches, which is the weight of a steel cylinder at 490 lb/ft³. Convert lineal feet to tonnage for pricing in the rebar weight calculator.

References

  • ACI 318-19, Building Code Requirements for Structural Concrete — American Concrete Institute
  • ASTM A615/A615M, Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement — ASTM International
  • ACI Detailing Manual (SP-066) — American Concrete Institute
  • Manual of Standard Practice — Concrete Reinforcing Steel Institute (CRSI)